• Electrical system calculation and design
• Electrical installation verification in accordance with NOM
• CFE Procedures
• Electrical Engineering
• 15KV medium voltage connection with air-to-underground transition
• Nema 3R Compact Substation — 15 KV
• 1500 kVA three-phase pad-mounted transformer
• Underground infrastructure, RMTB-4 records, corrugated PAD-type pipe
• 2000 Amps general distribution board
• 200 Amps electrical distribution boards
• Thermomagnetic switches from 15 to 200 Amps
• Electrical service outlets distribution, and protections
• Lighting system for production areas, offices, and bathrooms; emergency and exit lights were included